Active ProjectIn Progress
Retail Fitout — Southgate Commercial
Project Ref: SC-2025-047 · 1 Feb 2025 – 30 Jun 2025
Last updated 8 Jun 2026, 10:29 AM
Overall Project Completion
68 of 100 points complete
On track for 30 Jun 2025 delivery
Milestones Complete
4
of 8 total
Next Milestone Due
22 days
Plastering & Plasterboard
Tasks Completed
24 / 36
6 in progress
Deliverables Available
6
files ready to download
Project Milestones
Plasterboard sheeting underway. Geometric ceiling panels being set. Approx. 60% complete.
Task Completion by Phase
Phase 1 — Site Preparation & Framing
8/8 tasks100%
8 complete
Phase 2 — Ceiling, Bulkhead & Electrical
10/12 tasks83%
10 complete2 in progress
Phase 3 — Plastering, Lighting & Fit-Off
6/12 tasks50%
6 complete4 in progress2 not started
Phase 4 — Painting & Practical Completion
0/4 tasks0%
0 complete4 not started
Overall Task Summary
Completed
24In Progress
6Not Started
6Total Tasks36
Overall progress67%
Tasks by Phase