Active ProjectIn Progress

Retail Fitout — Southgate Commercial

Project Ref: SC-2025-047  ·  1 Feb 2025 – 30 Jun 2025

Last updated 8 Jun 2026, 10:29 AM
Overall Project Completion

68 of 100 points complete

On track for 30 Jun 2025 delivery

Milestones Complete
4

of 8 total

Next Milestone Due
22 days

Plastering & Plasterboard

Tasks Completed
24 / 36

6 in progress

Deliverables Available
6

files ready to download

Project Milestones

Plasterboard sheeting underway. Geometric ceiling panels being set. Approx. 60% complete.

Task Completion by Phase

Phase 1 — Site Preparation & Framing
8/8 tasks100%
8 complete
Phase 2 — Ceiling, Bulkhead & Electrical
10/12 tasks83%
10 complete2 in progress
Phase 3 — Plastering, Lighting & Fit-Off
6/12 tasks50%
6 complete4 in progress2 not started
Phase 4 — Painting & Practical Completion
0/4 tasks0%
0 complete4 not started
Overall Task Summary
Completed
24
In Progress
6
Not Started
6
Total Tasks36
Overall progress67%
Tasks by Phase